Restoration of platform subsidence at Törökbálint station

Restoration of platform subsidence at Törökbálint station

Investor: MÁV Zrt.
Client: MÁV Zrt.
Contractor: Homlok Zrt.
Start of the project: 07.04.2020
Project completion: 31.12.2020

Brief description of the project:

 

Homlok Zrt. carries out the construction works in the tendering procedure entitled „Restoration of platform subsidence at Törökbálint station and related overhead line, space lighting and telecommunication works Phase I” with the involvement of subcontractors.

Main technical content:

  • perform the necessary demolition work (retaining wall; platform; overhead line; space lighting; telecommunications)
  • extraction and removal of excess land from the incision (~ 2500 m3);
  • embankment construction of more than 10,000 m3
  • platform construction, cover made of single-element cladding, platform edging made of prefabricated platform elements;
  • overhead line construction work (column adjustment, support structure installation, overhead line control, column painting)
  • installation of passenger information systems
  • performing cable construction, telecommunications and space lighting works;

The work must be done in one step while maintaining the traffic of the railway plant and the local trains stopping at the station. According to the contract, there are 165 days to complete the project.


  • Beruházó:    MÁV Magyar Államvasutak Zrt.

  • Megrendelő:    

  • Kivitelező:    Homlok Építő Zrt.

  • Kivitelés kezdete:    2018

  • Kivitelés várható befejezése:    2020


Projekt rövid ismertetése:
   

The technical contents of the project include track maintenance operations on the track network of MÁV Zrt., as part of a framework contract. As part of this, Homlok Zrt. carries out servicing and maintenance operations based on two framework contracts:

  • Reconstruction of reinforced concrete bases in the track network of MÁV Zrt. –
    framework contract for the period 2018 – 2020
  • Replacement of cross-ties in the track network of MÁV Zrt. – framework contract for
    the years 2018 – -2020

Based on both framework contracts, the servicing operations of reinforced concrete bases and bore servicing operations, and the replacement of cross-ties in the bypasses, planned for the year 2018, were carried out according to the technical specifications. According to the contract, the operations will continue in the next two years.