The construction of the funeral home in NagysimonyiThe construction of the funeral home in Nagysimonyi
Constructor: The local government of Nagysimonyi
Client: The local government of Nagysimonyi
Contractor: Homlok Zrt.
Project start date: 25 January 2022
Project end date: 30 June 2022
Short description of the project:
According to the current service contract, Homlok Zrt. is responsible for the construction of a new mortuary in the public cemetery of Nagysimonyi village.
The following development work is carried out as part of the project:
- Construction of a new masonry building with a floor area of 60 m2 and a covered open space with a floor area of 90 m2, with stone surface paving
- Construction of barrier-free access and barrier-free bathrooms.
- Establishment of service rooms in the building
- Installation of infrared heating panels for intermittent use.
The performance period for the task is 5 months.